Planning and Infrastructure Act 2025

Article 86 of the Law — Powers of entry: compensation

(1) If damage is caused to land or other property in the exercise of a power of entry, a person suffering the damage may recover compensation from Natural England.

(2) Notice required to be given under section 83(3), 84(3) or 85(7)(b) must include a statement about the right to such compensation.

(3) Any question of disputed compensation under subsection (1) is to be referred to and determined by the Upper Tribunal.

(4) Section 4 of the Land Compensation Act 1961 (costs) applies to the determination of a question referred under subsection (3) as it applies to the determination of a question under section 1 of that Act, but as if references to the acquiring authority were references to Natural England.