Procurement Act 2023

Article 77 of the Law — Publication of modifications

(1) Before the end of the period of 90 days beginning with the day on which a contracting authority makes a qualifying modification under section 74(1), the authority must publish a copy of—

(a) the contract as modified, or

(b) the modification.

(2) A “qualifying modification” is a modification—

(a) in respect of which the contracting authority is required to publish a contract change notice under section 75, and

(b) which modifies, or results in, a public contract with an estimated value of more than £5 million.

(3) Subsection (1) does not apply in relation to a modification of a contract that—

(a) was awarded by a devolved Welsh authority, unless it was awarded as part of a procurement under a reserved procurement arrangement, or

(b) was awarded as part of a procurement under a devolved Welsh procurement arrangement.

(4) A Minister of the Crown may by regulations amend this section for the purpose of changing the financial threshold.